Ashburnham Solar is a 4MW solar farm built by groSolar for the Massachusetts utility Ashburnham Municipal Light Plant (AMLP).
Sort Projects By:
Featured Solar Installation Projects
-
4.00 MW
-
2.51 MW
-
4.30 MW
groSolar handled all aspects of design and construction of the Cambridge Solar Project in Dorchester County, MD on behalf of Constellation. Completed in early May 2015, the 4.3-megawatt (DC) grid-connected solar project provides clean energy to the National Aquarium as part of a 25-year competitive electricity supply agreement. groSolar supported OneEnergy Renewables with its early project development efforts and then worked through challenging winter conditions to construct the project on schedule for Constellation.
-
7.10 MW
groSolar designed and constructed the Marion County Solar project which combines two environmentally sensitive sites in order to deliver 7.1 megawatts of clean renewable solar energy. 5.2 megawatts were constructed on a capped landfill and 1.9 megawatts were constructed on a nearby brownfield. groSolar's experience in designing and constructing projects on environmentally sensitive sites resulted in a well-designed project easily constructed within the project's six-month schedule. Some of the project's unique engineering characteristics and design challenges included:
-
2.96 MW
Limerick Road Solar, LLC, is a 2.96 MW solar photovoltaic (PV) system in Shelburne, Vermont. The project is located on 15 acres of the 1,000-acre Meach Cove Farms, a privately owned certified organic farm which focuses on efficiently using local natural resources.
-
2.00 MW
groSolar was pleased to once again work with City of Rome, NY to develop a 2.0 Megawatt(AC) solar project upon vacant land, adjacent to a prison, and largely constrained by wetlands. While the site may have been undevelopable for more traditional infrastructure, groSolar was able to install nearly 9,000 panels in order to deliver renewable clean energy to the City of Rome. The project’s economic benefits include approximately $4 million in energy cost savings to the City of Rome over the project’s 20-year Power Purchase Agreement.
-
2.00 MW
groSolar engineered and constructed two solar arrays at OG+E’s Mustang Energy Center in west Oklahoma city – a 2 MW AC single axis tracking array and a 500 kW AC fixed tilt array. The completion of this project represents one of the most significant solar developments in the State of Oklahoma to date and is part of OG+E’s continued commitment to being an affordable, reliable, safe, and environmentally responsible energy provider. The Mustang Solar Project is unique in that it is designed as both a testbed of solar technology for OG+E while providing real power
-
2.00 MW
groSolar is pleased to be engaged by the City of Rome, NY to develop, design and construct a 2.0 Megawatt (AC) solar project on the closed and capped Tannery Road Landfill. This, otherwise undevelopable land, is ideal for repurposing as a solar electric generating project. The project will bring 3,400,000 kilowatt hours of clean, renewable electricity to the residents of Rome in the project’s first year.
-
663.00 kW
This 663 kW PV system was built on the rooftop of a campus headquarters in Bristol, Connecticut. groSolar was able to successfully address a number of challenges including maximizing the amount of energy production within the site constraints on the 150,000 square foot installation. All of the construction, electrical interconnection, and system testing needed to be completed in conjunction with the facility’s schedules and without interruption to the 24-hour operations of their TV network.
-
1.50 MW
Clean Harbors Environmental Services (NYSE: CLH) chose to install a solar power system at its Bridgeport, NJ, facility to offset more than 90% of the facility’s annual electric bill. Prior to the installation, the facility’s annual electric bill was $250,000.
Most of the facility’s electricity is used to run pump and treatment equipment to pump contaminated ground water, treat it and then discharge it into the Raccoon Creek. The 6,500+ PV modules sit on top of a capped landfill, which was thought to have no development potential.
-
2.49 MW
The Open View Solar Farm is a project of Cross Pollination, an organization which was created to promote the integration of renewable energy and sustainable organic farming. The 2.49MW solar PV system is located in New Haven, Vermont, and was installed on schedule and within budget.
The project is privately owned by Cross Pollination, Inc. and was designed and built by groSolar.
-
3.88 MW
The Berkley East Solar Power Project is a 3.88 MW DC municipal utility-tied solar PV system. This Massachusetts project was built by groSolar on previously undeveloped land and was completed ahead of schedule. Construction began by sensitively excavating the rocky land surrounded by cranberry bogs and a newly created turtle habitat. The energy generated from the system will be purchased by Taunton Municipal Lighting Plant (TMLP), the largest municipal electric utility in the state.
-
5.40 MW
-
1.20 MW
SAS Institute, Inc., the world leader in business analytics software and services, is the largest vendor in the business intelligence market. SAS is fully committed to sustainability with an existing megawatt solar electric array at their Cary, NC headquarters. They reaffirmed their commitment to sustainable practices with the addition of SAS Solar Farm 2, a 1.2 MW PV project that creates enough power for more than 700 homes.
-
105.30 kW
Worcester State College (WSC) has joined the green revolution. WSC has a commitment to sustainability and has incorporated many upgrades and improvements into their overall sustainability plan, including the purchase of a biodiesel processor, conservation efforts and increased recycling. Another part of their plan, was installing a 105.3 kW solar array on their Learning Resource Center which was funded by IRS Clean Renewable Energy Bonds and a grant from the Massachusetts Technology Collaborative. The photovoltaic array will generate over 140,000 kW hours of electricity a
-
1.50 MW
Longwood Gardens of Kennett Square, PA has made an institutional commitment to install 1.5 MW of photovoltaic power, providing approximately 18% of the international tourist destination’s electricity. The grid-tied installation, consisting of two ground-mount arrays, will reduce Longwood’s annual carbon dioxide emissions by 1,367 tons and produce enough electricity to power over 1000 homes. groSolar worked close with Longwood Gardens to incorporate the solar modules into the natural beauty and landscape at the site.